PostSubject: Cost vs COP   Cost vs COP Icon_minitimeSat Oct 27, 2012 5:15 pm

Our cost savings analysis is indicating a different operating configuration than our best COP. Which is more important in this case? Should we go with the best cost savings and then just report the COP and Ts diagram for this case? bounce
Back to top Go down
View user profile
GSI Overlord
Admin


Posts : 126
Join date : 2012-08-30

Cost vs COP Empty
PostSubject: Re: Cost vs COP   Cost vs COP Icon_minitimeSat Oct 27, 2012 6:31 pm

This is a really important question, and frankly it's quite critical to addressing the main deliverable in the task letter. Hopefully others will look at this as well.

The bottom line is to find the cheapest solution for the client; as with many engineering problems (and most situations) in real life, the almighty dollar drives everything. The client doesn't really care about the thermodynamic efficiency of the cycle, they just care about bottom line cost. So your optimal cycle and final recommendation will hinge on minimizing cost, not on maximizing COP.
Back to top Go down
View user profile http://fall2012me395.forumotion.com
 
Cost vs COP
Back to top 
Page 1 of 1
 Similar topics
-
» How much does a credit cost
» Cost of credits
» Milk available in Wynnewood, PA
» Milk Needed on Whidbey Island
» The ruling that cost Baby P his life

Permissions in this forum:You cannot reply to topics in this forum
Fall 2012 ME 395 - GSI Josh Lacey :: Lab Questions :: Lab 5-
Jump to: